Switchboards

Switchboard hire for your temporary power needs

It is common industry practice for electrical contractors to provide temporary electrical supply installations for commercial construction sites.

Sometimes, only a single temporary switchboard will be needed, such as for the construction of a single dwelling, but in other circumstances it may be necessary to have multiple switchboards, including some permanent switchboards, in more than one location on–site. This may be the case for larger construction jobs.

 

Temporary Electrical Switchboard (Standards & Safety)

Quality standard switchboards

Regardless of the number or type of switchboards, they must all:

  • be weatherproof; 
  • be robust and constructed with materials able to withstand mechanical damage from environmental or other influences that may be expected at the location, such as construction equipment;
  • have a means to prevent strain/damage to cables and cords, such as the use of a tie-bar;
  • have no exposed live parts;
  • be clearly marked with numbers or letters to identify each one from other switchboards on the site;
  • have a lid/door which:
    • can be opened without removing or damaging any cables or cords;​
    • is lockable; and
    • can remain open whilst an operator works on the switchboard.
  • be safely and securely mounted to a permanent structure such as a wall, or secured to a temporary post or pole, be freestanding or suitably designed for the purpose;
  • have each socket outlet provided on the switchboard for the connection of portable equipment individually controlled by a double pole switch or other device that provides the same level of safety as a double pole switch; and
  • have all components legibly marked to indicate their relationship with various sections of the installation.

Also:

  • switchboards must be within easy reach and located so that the maximum length of flexible cord is not exceeded (note: maximum length of flexible cord is approximately 30 metres);
  • flexible cords and cables shall be supported off the floor or ground on insulated stands or hooks; and 
  • flexible cords must be confined to the level of the switchboard they originate from (except in lift shafts or stairwells).

RCD protection

All final sub circuits on switchboards are to be protected by residual current devices (RCDs) with a maximum rated residual current of 30mA.

Testing and inspection

All routine testing and inspections of switchboards must be carried out by a licensed electrical worker. Any equipment that fails testing must be withdrawn from use and not returned to service until it has been repaired and re-tested.

A licensed electrical worker is also required to visually inspect and test all construction wiring, which includes switchboards. Unlike portable equipment, which must be inspected every three months, switchboards must be inspected at least every six months.

The results of the inspections and tests must be recorded and kept on site.

More information?

For further information, check out WorkSafe’'s website or contact WorkSafe on 1300 307 877.